Below is the construction timeline on Route 302:

Sunday, September 8 to Monday, September 23 construction will consist of milling and paving shoulders from the Angler Road and Whites Bridge intersection approximately 7200 feet to the Windham Christian Academy - night work.

Tuesday, September 24 to Monday, September 30, construction will consist of shimming and surfacing.

Tuesday, October 1, construction will consist of hand work and stripping

Wednesday, October 2 to Thursday, October 3, construction will consist of back shoulders and gravel driveways.

The above schedule may change due to weather or other unforeseen circumstances.